11/17/2026 Resolutions 2026-320 RESOLUTION 2026-320
WHEREAS, the City Engineer/Public Works Director for the City Of Grand
Island has issued a Certificate of Completion for Sanitary Sewer Manhole Rehabilitation; Project
No. 2025-S-2, certifying that Midlands Contracting dba Johnson Service Co. of Kearney,
Nebraska, under contract, has completed such work in the total amount of$465,028.15; and
WHEREAS, additional project costs equate to $80,808.69, as detailed below,
resulting in a total project cost of$545,836.84; and
Grand Island Independent- Advertising $ 60.40
Grand Island Public Works- Engineering Services S 16,852.68
Olsson, Inc.- Engineering Services S 63,895.61
Additional Project Costs $80,808.69
WHEREAS, the City Engineer/Public Works Director recommends the
acceptance of the project; and
WHEREAS, the Mayor concurs with the recommendation of the City
Engineer/Public Works Director.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL
OF THE CITY OF GRAND ISLAND, NEBRASKA, that the Certificate of Final Completion,
for Sanitary Sewer Manhole Rehabilitation; Project No. 2025-S-2 in the total amount of
$545,836.84, is hereby confirmed.
Adopted by the City Council of the City of Grand Island,Nebraska,November 17, 2026.
Ro r G. Steel Mayor
Attest:
Ji ranere, City Clerk