04/13/2010 Resolutions 2010-100RESOLUTION 2010-100
WHEREAS, General Electric International was awarded the contract for On-Site
Technical Inspection at the December 15, 2009 City Council meeting; and
WHEREAS, the specifications required a firm bid based on an estimated project
schedule oftwo weeks, with unit pricing to adjust the total cost based on actual project duration; and
WHEREAS, the combustion inspection of GT3 required an additional five days of
technical advisor time to complete, at an additional cost of $12,800.00 per the contract pricing, for a
final contract cost of $55,402.05.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 with General Electric
International resulting in an additional cost of $12,800.00 for a final contract price of $55,402.05, is
hereby approved.
Adopted by the City Council of the City of Grand Island, Nebraska, April 13, 2010.
Margaret rnady, ayor
Attest:
~a~~ ~~~~
RaNae Edwards, City Clerk
~i
Approved as to Form n
April 12, 2010 a City Attorney