01/26/2010 Resolutions 2010-32RESOLUTION 2010-32
WHEREAS, Van Kirk Brothers Contracting, of Sutton, Nebraska was awarded the
contract for construction of Water Main Project 2009-W-3; a water line to the Village of Alda; and
WHEREAS, the City of Grand Island and the surrounding area received record snow
falls and below freezing temperatures in the month of December, 2009; and
WHEREAS, Van Kirk's bid originally anticipated 185 days from the Notice to
Proceed to complete the project, that completion date being February 6, 2010; and
WHEREAS, due to the adverse weather conditions, Van Kirk Brothers Contracting is
requesting a 90 day extension to the contract to complete the contract requirements; and
WHEREAS, the extension does not change the dollar amount of the contract.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 with Van Kirk Brothers
Contracting, of Sutton, Nebraska resulting in a time extension of 90 days, for a new completion date
of May 6, 2010, is hereby approved.
Adopted by the City Council of the City of Grand Island, Nebraska, January 26, 2010.
Margar Hornady, Mayor
Attest:
~4
RaNae Edwards, City Clerk
Approved as to Form a ~~
January 25, 2010 ~ City Attorney