01/12/2010 Resolutions 2010-5RESOLUTION 2010-5
WHEREAS, Natgun Corporation of Wakefield, MA was awarded a contract for
Rogers Reservoir Tank Improvements Water Project, such bid being in the amount of$1,772,300.00;
and
WHEREAS, during construction, it was discovered that the elevation ofthe existing
36" outlet header line was located 3.1 feet higher than what was shown on the as-built plans from
1979; and
WHEREAS, an additional 22.5 degree elbow and thrust block were required, along
with additional time by the piping sub-contractor to install the elbow and align the existing pipe with
the new pipe, and install the thrust block; and
WHEREAS, the additional elbow installation and alignment ofthe existing pipe with
the new pipe was not included in the original contract award and the contractor provided a price
quote for the additional work of $26,201.00; and
WHEREAS, the net cost of the changes to the original contract is $26,201.00 for a
final contract amount of $1,798,501.00
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 with the Natgun
Corporation of Wakefield, MA resulting in an addition of $26,201.00 to the original contract amount
of $1,772,300.00 for a final contract amount of $1,798,501.00 for Rogers Reservoir Tank
Improvements Water Project is hereby approved.
Adopted by the City Council of the City of Grand Island, Nebraska, January 12, 2010.
!~. ~~~ ~
Margar Hornady, Mayor.ti
Attest:
O.R.,
RaNae Edwards, City Clerk
Approved as to Form u
January 13, 2010 o City Attorney