03/04/2003 Resolutions 2003-64
I
I
I
RES 0 L UTI 0 N 2003-64
WHEREAS, on December 4, 2001, by Resolution 2001-328, the City Council for the
City of Grand Island awarded the bid for general contract work on combustion turbines at Burdick
Station to The Industrial Company of Steamboat Springs, Colorado; and
WHEREAS, it has been determined that modifications to the work to be performed by
The Industrial Company are necessary; and
WHEREAS, such modifications have been incorporated into Change Order No.4;
and
WHEREAS, the result of such modifications will increase the contract amount by
$1,650,772.00 for a total contract price of $13,962,822.42.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE CITY OF
GRAND ISLAND, NEBRASKA, that the Mayor is hereby authorized and directed to execute
Change Order No.4, between the City of Grand Island and The Industrial Company of Steamboat
Springs, Colorado to allow the modifications set out in Exhibit "A" attached hereto.
Adopted by the City Council of the City of Grand Island, Nebraska, March 4,2003.
QcStcu y.l)w~
RaNae Edwards, City Clerk
Approved as to Form II
February 27, 2003
I
I
I
Summary of Chan~e Order No.4:
Revised cable tabulation for additional substation control and relaying
circuits, as vendor and City information was received for final design.
Revised switchyard drawings - added 4,000 feet of cable for grounding,
increased size from 250 to 500 kcmil.
Revised electrical drawings and schematics for balance of Plant relays,
metering, and lockout relays.
Revised cable tabulation - relocated Distributed Control System cabinet
from turbine floor to Electrical Equipment Building.
Heat trace due to drawing revisions - from adding fuel oil piping to GT-1
to eliminate 35 year old piping on GT-1 and add it to the new system.
Premium time to improve schedule delay.
Productivity loss impact due to GE material delivery.
$ 60,178.00
$ 54,860.00
$ 76,187.00
$ 66,877.00
$ 10,302.00
$ 135,743.00
$1,096,911.00
PCC relay panels - additional breaker failure relays, verification of existing $ 121,569.00
circuits, and additional electrical testing were required to complete full integration
to the existing Grand Island systems.
Burdick control room panel - finalized protective relaying, additional electrical
testing for full systems integration.
Fuel pump control panel added relaying for dual pump sequencing. Original
GE design had two, dual pump skids. Pump design was revised to a single
dual pump skid.
GEEPE fuel oil tubing rework.
$ 16,203.00
$ 8,177.00
$ 3,765.00
$1,650,772.00
TOTAL
EXHIBIT "A"