WHEREAS, on December 4,2001, by Resolution 2001-328, the City Council for the
City of Grand Island awarded the bid for general contract work on combustion turbines at Burdick
Station to The Industrial Company of Steamboat Springs, Colorado; and
WHEREAS, it has been determined that modifications to the work to be performed by
The Industrial Company are necessary; and
WHEREAS, such modifications have been incorporated into Change Order No.3;
and
WHEREAS, the result of such modifications will increase the contract amount by
$325,537.00 for a total contract price of $12,312,050.42.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE
CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No.3, between the City of Grand Island and The Industrial
Company of Steamboat Springs, Colorado to provide the following modifications:
Amount
Substation electrical revisions................................... ................................................................. $ 45,986.00
Provide conduit for fiber-optic cable ............................................................................................. 11,281.00
Sewer and underground pipe revisions ............ ................. .............................. ....... .............. ........ 113 ,327 .00
Delete chemical cleaning for demineralized water piping ..............................................................(3,027.00)
Provide grounding for fuel oil piping ............................................................................................ 21,986.00
Provide additional access platforms & vents.................................................................................. 67,397.00
115 kV breaker repair........ ....................... ........... .......................................................................... 14,238.00
Provide additional grounding for generator transformer .....................................................................415.00
Provide additional pipe heat tracing.......... ....................................................................................... 1,995.00
Provide additional anchoring for frame cooling blowers .................................................................9,821.00
Provide shielding for control wiring.. ........................ ................. ....... ....... ............................ ...........2,988.00
Provide additional pipe insulation........ ............................................................................................ 3,606.00
Deduct for damaged cable replacement ............................... ....... ....... ..................... .............. .......... (2,596.00)
Change for transformer enclosure material......... ........................ ....... ................................... .......... (6,887.00)
Delete seeding of site.................. ....... ....... .................................................................................... (16,043 .00)
Thermocouple cable revision ......................................................................................................... 12,318.00
Start-up work........................... ....... ......... ................................... ....... ....... ....... .............. ........... .....47,368.00
Backcharges to GEEPE ........... ......... .............................................. ..... ......... ..... .............. ................ 1,364.00
Adopted by the City Council of the City of Grand Island, Nebraska, January 28,2003.
Qf\no ffi[A~t\~Dv
RaNae Edwards, City Clerk
Approved as to Form xx ):j0...S
January 24, 2003 xx City Attorney