10/08/2002 Resolutions 2002-315
I
I
I
RESOLUTION 2002-315
WHEREAS, on December 4, 2001, by Resolution 2001-328, the City Council for the
City of Grand Island awarded the bid for general contract work on combustion turbines at Burdick
Station to The Industrial Company of Steamboat Springs, Colorado; and
WHEREAS, it has been determined that modifications to the work to be performed by
The Industrial Company are necessary; and
WHEREAS, such modifications have been incorporated into Change Order No.1;
and
WHEREAS, the result of such modifications will increase the contract amount by
$705,382.43 of which $197,558.43 is back charged to equipment suppliers for changes or additions
to their equipment.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No.1, between the City of Grand Island and The Industrial
Company of Steamboat Springs, Colorado to provide the modifications as outlined on Exhibit "A"
attached hereto and incorporated herein by reference.
Adopted by the City Council of the City of Grand Island, Nebraska on October 8, 2002
QS\~_ ~~
RaNae Edwards, City Clerk
Approved as to Form T ~
October 3. 2002 ... City Attorney
I City of Grand Island
Utilities Department
General Work Contract - Change Order 1
(submitted with Memo 10/1/02)
Change
Order
Request Description Amount
001 Add warehouse rebar splices $ 2,650.00
002 Backcharge to GEEPE $ 4,371.00
003 Revise substation caissons $ 44,034.00
004 Revisions to fuel oil pipe support and turbine
control center foundations $ 9,689.00
005 Revise fuel oil heater foundation $ 4,431.00
006 Revise stack, fuel filter, water injection, and
transformer foundations $ 10,617.00
007 Delete pipe vault $ (5,611.00)
008 Add insulation and heat trace to fuel oil piping $ 547.00
009 Delete demineralized water valves $ (2,153.00)
010 Revisions to construction issue piping drawing set $ (10,376.00)
011 Revisions to fire loop pipe specifications $ 56,~12.00
012 Revise fuel oil piping support design $ 45,538.00
I 013 Revisions to fencing and pavement, add fuel oil
pipe bridge $ 59,300.00
014 Add instrument devices $ 6,848.00
015 Revise electrical one-line diagram $ 5,016.00
017 Revise circulating water piping $ 55,958.00
018 Revise demineralized water piping $ 1,498.00
019 Revise fuel oil pump house piping $ 70,000.00
020 Revision to site piping plan drawings $ 21,627.00
021 Revise oil/water separator foundation and
manhole extentions $ 41,965.00
023 Backcharges to GEEPE $ 68,068.01
024 Revisions to Instrument Index $ (2,313.00)
028 Delete road textile underlayment $ (3,781.00)
029 Revise tunnel pavement $ 77,000.00
030 Revise auxiliary transformer foundations $ 2,944.00
031 Delete HV AC filtering section $ (11,900.00)
032 Relocate fire water piping $ 5,127.00
033 Relocate fire water hydrant $ 6,476.00
034 Add circulating water valves $ 5,481.00
035 Backcharges toGEEPE $ 34,846.42
036 Add fuel oil tank floating suction $ 10,900.00
I 037 Backcharge to Varmont $ 959.00
039 Backcharges to GEEPE $ 89,314.00
Total $705,382.43
Exhibit "A"