03/13/2000 Resolutions 2000-79
I
I
I
RES 0 L UTI 0 N 2000-79
WHEREAS, on November 8, 1999, by Resolution 99-353, the City of Grand Island
concurred with the Nebraska Department of Roads for the bid award for construction of a Federal
Aid Project including grading, culverts, bridge, concrete pavement and utilities on South Locust
Street from U.S. Highway 34 south to the Wood River Floodway to Werner Construction Co. of
Hastings, Nebraska under State Contract NDOR #STPAA-5414(l) CN 41415; and
WHEREAS, it has been determined that modifications to the work to be performed
by Werner Construction Co. are necessary to install additional sanitary sewer along Lake Street and
South Locust Street; and
WHEREAS, such modification has been incorporated into a change order dated
February 23, 2000; and
WHEREAS, this change order will result in a net increase to the contract in the
amount of $112,550.1 O.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute the change order dated February 23, 2000, between the City of Grand Island and
Werner Construction Co. to provide the following modifications:
[4910.25] Dewatering (207.11 @ $76.56) ......................................................................................15,856.34
[4731.10] 250 rom Sanitary Sewer Pipe (923.680 @ $56.25) ......................................................... 51,957.00
[4731.06] 150 rom Sanitary Sewer Pipe (27.040 @ $37.74).............................................................1,020.49
[4016.11] Manhole Sanitary Sewer (9 @ $1,960.42).............................................:........................ 17,643.78
[4015.75] Manhole Sanitary Sewer (22.937 @ $549.44) ................................................................12,602.51
[4042.55] Connect Sanitary Sewer (15 @ $366.82) ......................................................................... 5,502.30
[4790.00] Sanitary Sewer Crossing (3 @ $541.89) .............. ................. ..................................... ...... 1,625.67
[2001.00] Gravel Surface Course (132 em@ $11.85) ...................................................................... 1,564.20
[6960.51] Compensation for Additional Handling Cost (1 @ $1,185.00) ........................................ 1,185.00
[2009.10] Gravel Embedment (2.151 @ $1,235.85) ......................................................................... 2,658.31
[4017.00] Tapping Existing Sanitary Sewer Manhole (1 @ $934.50) ................................................. 934.50
Adopted by the City Council of the City of Grand Island, Nebraska on March 13,2000.
,..
Approved as to Form" c..gt...
March 9, 2000 ... City Attorney