09/08/2009 Resolutions 2009-213RESOLUTION 2009-213
WHEREAS, on June 23, 2009, by Resolution 2009-141, the City Council ofthe City
of Grand Island approved the bid of Galvan Construction, Inc. of Grand Island, Nebraska for the
construction of Handicap Ramp Project Number 2009-1; and
WHEREAS, the completion of such project has been delayed due to restricted access
to the handicap ramp installation areas from the 2009 Asphalt Resurfacing Project; and
WHEREAS, Galvan Construction, Inc. has requested a contract time extension from
September 1, 2009 to October 15, 2009 in order to complete this project; and
WHEREAS, the Public Works Department supports such contract time extension.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the completion date for the construction of
Handicap Ramp Project No. 2009-1 is hereby extended to October 15, 2009.
BE IT FURTHER RESOLVED, that the Mayor is hereby authorized and directed to
execute such contract time extension on behalf of the City Of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, September 8, 2009.
Margaret ornady, Mayor
Attest:
RaNae Edwards, City Clerk
Approved as to Form n
September 8, 2009 a City Attorney