06/23/2009 Resolutions 2009-144RESOLUTION 2009-144
WHEREAS, the City Electric Department invited sealed bids for Burdick Cooling
Tower Piping Modifications; and
WHEREAS, on December 30, 2008, bids were received, opened and reviewed; and
WHEREAS, Judds Brothers Construction CompanyofLincoln,Nehraska submitted a
bid in accordance with the terms of the advertisement of bids and plans and specifications and all
other statutory requirements contained therein, such bid being in the amount of $266,125; and
WHEREAS, after excavation work began, unsuitable materials were found in the
underlying soil which prevented the soil from being reused, and clean fill was hauled in and placed to
provide firm support for the new piping; and
WHEREAS, old piping and supports needed to be repaired or modified for equipment
installation to accommodate the new.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 for Judds Brothers
Construction Company of Lincoln, Nebraska, in the amount of $14,910.02, for a total contract cost
of $281,035.02, for Cooling Piping Modifications at Burdick Station, is hereby approved.
Adopted by the City Council of the City of Grand Island, Nebraska, June 23, 2009.
Margar Hornady, ayor
Attest:
~~a~..~,
RaNae Edwards, City Clerk
Approved as to Form
June 22, 2009 p City Attorney