03/11/2025 Resolutions 2025-79 RESOLUTION 2025-79
WHEREAS, the City Engineer/Public Works Director for the City Of Grand
Island has issued a Certificate of Completion for Wastewater Treatment Plant Flow
Improvements; Project No. 2020-WWTP-4 (the "Project"), certifying that Building Crafts, Inc.
of Red Oak, Iowa, under contract, has completed the project for the total amount of
$8,609,018.29; and
WHEREAS, the City has incurred additional project costs in the amount of
$1,136,848.15, as detailed below, resulting in a total Project cost of$9,745,866.44; and
Additional Project Costs-
HDR Engineering, Inc.- Engineering Services $ 1,036,197.07
Grand Island Public Works- Engineering Services $ 69,931.57
Dakota Hogback Automation, Inc.- SCADA Programming $ 16,873.41
Construction Rental- Equipment Rental $ 82.50
McMasterCarr- Winch $ 3,630.63
Nunnenkamp Well Co., Inc.- Dewatering Well $ 9,995.00
Grand Island Independent- Advertising $ 137.97
Additional Project Costs $ 1,136,848.15
WHEREAS, the City Engineer/Public Works Director recommends the
confirmation of the Certificate of Final Completion and acceptance of the Project as complete;
and
WHEREAS, the Mayor concurs with the recommendation of the City
Engineer/Public Works Director.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL
OF THE CITY OF GRAND ISLAND, NEBRASKA, that the Certificate of Final Completion,
for Wastewater Treatment Plant Flow Improvements; Project No. 2020-WWTP-4, in the total
amount of$9,745,866.44, is hereby confirmed and the Project is hereby accepted as complete.
Adopted by the City Council of the City of Grand Island, Nebraska, March 11, 2025.
Rog G. Steele, Mayor
Attest:
ig/n4iyatde. 40
Jill Granere, City Clerk