02/13/2024 Resolutions 2024-41R E S O L U T I O N 2024-41
WHEREAS, at the August 8, 2023, Council meeting, GE Steam Power, Inc., was
awarded the contact for the Platte Generating Station Turbine Overhaul 2023 in the amount of
$1,516,077.00; and
WHEREAS, the amount of actual work required could not be known until the unit
was disassembled and inspected; and
WHEREAS, additional repairs discovered during the inspection resulted in additional
costs of $405,473.52 for a final contract cost of $1,921,550.52.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 with GE Steam Power, Inc.,
in the total amount of $405,473.52, is approved, and the Mayor is hereby authorized to sign the
Change Order on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, February 13, 2024.
;
,�