12/05/2023 Resolutions 2023-313RESOLUTION 2023-313
WHEREAS, on July 12, 2022, via Resolution No.2022-179, the City of Grand Island
awarded SKM Turnkey Construction, LLC of Grand Island, Nebraska the bid in the amount of
$2,045,489.30 for Lift Station No. 28 Equalization Tank; Project No. 2022-5-3; and
WHEREAS, on November 22, 2022, via Resolution No. 2022-328, City Council
approved Change Order No. 1 to the project to rectify quantities, upsize the valve manhole, remove
existing jib crane, modify the proposed wash down system to fit the site conditions, add additional
storm sewer to remedy existing field condition, and other miscellaneous fittings required now that
work is underway; and
WHEREAS, Change Order No. 1 resulted in a contract increase of $31,245.07, for a
revised contract amount of $2,076,734.37; and
WHEREAS, it is necessary to further rectify quantities for the project; and
WHEREAS, such modifications have been incorporated into Change Order No. 2 at a
cost of $36,999.42; and
WHEREAS, approval of Change Order No. 2 as recommended by staff requires an
increase in the total contract amount to $2,113,733.79.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 2 in the amount of $36,999.42 and increase the amount of the
contract between the City of Grand Island and SKM Turnkey Construction, LLC of Grand Island,
Nebraska to a total contract price of $2,113,733.79 for Lift Station No. 28 Equalization Tank; Project
No. 2022-S-3.
Adopted by the City Council of the City of Grand Island, Nebraska, December 5, 2023.
.