10/10/2023 Resolutions 2023-254R E S O L U T I O N 2023-254
WHEREAS, the City Engineer/Public Works Director for the City Of Grand
Island l�as issued a Certificate of Completion for Project No. 2023-AG1, Asphalt Resurfacing,
certifying that Gary Smith Construction Co., Inc. of Grand Island, Nebraska, under contract, has
completed the asphalt resurfacing in the total amount of $723,197.77; and
WHEREAS, additional project costs equate to $43,071.14, as detailed below,
resulting in a total project cost of $766,268.91; and
WHEREAS, the City Engineer/Public Works Director recommends the
acceptance of the project; and
WHEREAS, the Mayor concurs with the recommendation of the City
Engineer/Public Works Director.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL
OF THE CITY OF GRAND ISLAND, NEBRASKA, that the Certificate of Final Completion,
for Project No. 2023-AG1, Asphalt Resurfacing, in the total amount of $766,268.91, is hereby
confirmed.
Adopted by the City Council of the City of Grand Island, Nebraska, October 10, 2023.
%� '�
Rog G. Steele, Mayor
Attest:
Ji Granere, Deputy City Clerk