09/12/2023 Resolutions 2023-220R E S O L U T I O N 2023-220
WHEREAS, the City Engineer/Public Works Director for the City Of Grand
Island has issued a Certificate of Completion for Capital Avenue- Moores Creek Drainway to
North Road Roadway Improvements; Project No. 2020-P-1 (the "Project"), certifying that
Elsbury Construction, LLC of Grand Island, Nebraska, under contract, has completed the work
required by the contract at a total cost of $1,510,273.55; and
WHEREAS, the City has incurred additional Project costs in the amount of
$483,513.50, as detailed below, resulting in a total Project cost of $1,993,787.05; and
BARBARA M WIECZOREK TEMP EASEMENT $ 510.00
CITY OF GRAND ISLAND PW ENGINEERING SERVICES $ 25,754.15
CITYOF GRAND ISLAND CURB MILLING $ 335.00
CITYOF GRAND ISLAND STORM SEWERTELEVISING $ 1,471.50
HALL COUNTY REGISTER OF FILING FEES $ 254.00
HOPE E NELSEN TEMP EASEMENT $ 210.00
JAMESTINNELL TEMP EASEMENT $ 470.00
JANICE E DYER TEMP EASEMENT $ 320.00
LEE BHM CORP ADVERTISING $ 38.85
MARTIN MONTELONGO TEMP & PERMANENT EASEMENT $ 470.00
OLSSON INC PRELIMINARY & CONSTRUCTION ENGINEERING $ 452,750.00
TL AN DERSON TEMP & PERMAN ENT EASEMENT $ 930.00
ADDITIONAL PROJECT COSTS= $ 483,513.50 '
WHEREAS, the City Engineer/Public Works Director recommends the
confirmation of the Certificate of Completion and acceptance of the Project as complete; and
WHEREAS, the Mayor concurs with the recommendation of the City
Engineer/Public Works Director.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL
OF THE CITY OF GRAND ISLAND, NEBRASKA, that the Certificate of Final Completion,
for Capital Avenue- Moores Creek Drainway to North Road Roadway Improvements; Project
No. 2020-P-1, in the total amount of $1,993,787.05, is hereby confirmed and the Project is
hereby accepted as complete.
Adopted by the City Council of the City of Grand Island, Nebraska, September 12, 2023.
Attest:
�
�,Gt U I' ��rt�'L
Ji Granere, Deputy City Clerk