11/22/2022 Resolutions 2022-326RESOLUTION 2022-326
WHEREAS, the City Engineer/Public Works Director for the City Of Grand
Island has issued a Certificate of Completion for Project No. 2022-AC-1, Asphalt Resurfacing
(the "Project"), certifying that Gary Smith Construction Co., Inc. of Grand Island, Nebraska,
under contract, has completed the work required by the contract at a total cost of $862,815.60;
and
WHEREAS, the City has incurred additional Project costs in the amount of
$48,061.76, as detailed below, resulting in a total Project cost of $910,877.36; and
Olsson Inc. — Pavement Cores & uali Assurance $ 4 768.00
Grand Island Inde endent- Advertisin 131.10
Ci of Grand Island Public Works En ineerin Services 43,162.66
Additional Pro'ect Costs $ 48,061.76
WHEREAS, the City Engineer/Public Works Director recommends the
confirmation of the Certificate of Completion and acceptance of the Project as complete; and
WHEREAS, the Mayor concurs with the recommendation of the City
Engineer/Public Works Director.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL
OF THE CITY OF GRAND ISLAND, NEBRASKA, that the Certificate of Final Completion,
for Project No. 2022-AC-1, Asphalt Resurfacing, in the total amount of $910,877.36, is hereby
confirmed and the Project is hereby accepted as complete.
Adopted by the City Council of the City of Grand Island, Nebraska, November 22, 2022.
�
Ro G. Steele, Mayor
Attest:
�C�ti��
RaNae Edwards, City Clerk
Approved as to Form tt �
November 21, 2022 tt City Attorney