09/13/2022 Resolutions 2022-257R E S O L U T I O N 2022-257
WHEREAS, on July 27, 2021 by Resolution 2021-180, August 24, 2021 by
Resolution 2021-208 and October 26, 2021 by Resolution 2021-297 the City Council of the City of
Grand Island awarded Diamond Engineering Co. of Grand Island, Nebraska, the bid in the amount of
$618,752.16, Change Order #1 amount (-$15,952.00) and Change Order #2 amount $231,500.00 for
the JBS Connector Trail Construction; and
WHEREAS, additional items were found to be required for the successful
completion/enhancement of the project; and
WHEREAS, such modifications will be funded through the JBS Donation Account
and Food and Beverage Tax; and
WHEREAS, such modifications have been incorporated into Change Order No. 3;
.F�I
WHEREAS, the result of such modifications will increase the contract amount by
$14,060.00 for a revised contract price of $848,360.16.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 3 between the City of Grand Island and Diamond Engineering
Co. of Grand Island, Nebraska to provide the modifications set out as follows:
1. New Trail Bridge Railing ........................................................ increase $2,900.00
2. Construct French Drain ............................................................increase $2,200.00
3. Construct Retaining Wall to Protect Utility Pole ..............................increase $6,960.00
4. Add Four (4) Concrete Barricades ...............................................increase $2,000.00
Adopted by the City Council of the City of Grand Island, Nebraska, September 13, 2022.