05/24/2022 Resolutions 2022-143RESOLUTION 2022-143
WHEREAS, the City Engineering/Public Works Director for the City of Grand Island issued
a Certificate of Final Completion for Parking Ramp Maintenance & Repairs- 2021; 103 North Locust
Street certifying that Wilkinson Industrial of Shelton, Nebraska, under contract, has completed such project
for the total construction amount of $71,988.00; and
WHEREAS, the City Engineer/Public Works Director recommends the acceptance of the
project; and
WHEREAS, additional project costs equate to $1,856.66, as shown
ADDITIONAL COSTS
Ci of Grand Island- PW En ineerin En ineerin Services $ 1,743.23
Grand Island Inde endent Advertisin $ 113.43
$ 1, 856.66
WHEREAS, the Mayor concurs with the recommendation of the City Engineer/Public
Works Director.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE
CITY OF GRAND ISLAND, NEBRASKA, that the Certificate of Final Completion for Parking Ramp
Maintenance & Repairs- 2021; 103 North Locust Street, in the total amount of $73,844.66 is hereby
confirmed.
Adopted by the City Council of the City of Grand Island, Nebraska, May 24, 2022.
Ro G. Steele, Mayor
Attest:
� � �.���,.�
RaNae Edwards, City Clerk
Approved as to Form II
May 23, 2022 II City Attorney