09/14/2021 Resolutions 2021-222RESOLUTION 2021-222 WHEREAS, Water Main Project 2021-W-3 a 6" diameter ductile iron water main along Sycamore Street from 22"d Street to Capital Avenue; and WHEREAS, the original contract was awarded by Council on October 13, 2020, in the amount of $96,115.00 to Van Kirk Sand & Gravel, Inc., d/b/a Van Kirk Bros. Contracting, of Sutton, Nebraska; and WHEREAS, during the process of constructing the water main, materials were added or deducted to complete the work and unit prices were provided in the Contract and specified that the contractor be paid on the basis of actual quantity installed, times the Contract's unit price; and WHEREAS, the original contract amount was $96,115.00, and the total changes to the contract amount was a deduct of $2,992.90, resulting in a final contract cost of $93,122.10. NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 for the construction of Water Main Project 2021-W-3 in the amount of a deduct of $2,992.90, is approved, and the Mayor is hereby authorized to sign the Change Order on behalf of the City of Grand Island. Adopted by the City Council of the City of Grand Island, Nebraska, September 14, 2021. oger G. Steele, Mayor Attest: �� o.e_ ( �l RaNae Edwards, City Clerk I'�_ - Approved as to Form tt September 13, 2021 � City Attorney