07/13/2021 Resolutions 2021-160RESOLUTION 2021-160
WHEREAS, on September 22, 2020, via Resolution 2020-238, the City of Grand
Island awarded The Diamond Engineering Company of Grand Island, Nebraska the bid in the
amount of $678,366.25 for Sanitary Sewer District No. 544; Ellington Pointe and Westwood Park
Subdivision; and
WHEREAS, the completion of such project has been delayed due to inclement
weather and drainage issues; and
WHEREAS, The Diamond Engineering Company has requested a substantial
completion date change from July 15, 2021 to August 9, 2021; and final completion date from July
22, 2021 to August 16, 2021 in order to complete the project; and
WHEREAS, there will not be any contract amount modification with such time
extension; and
WEREAS, the Public Works Department supports such contract extension.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 1 between the City of Grand Island and The Diamond
Engineering Company of Grand Island, Nebraska to provide the requested time extension for
Sanitary Sewer District No. 544; Ellington Pointe and Westwood Park Subdivisions.
Adopted by the City Council of the City of Grand Island, Nebraska, July 13, 2021.