12/22/2020 Resolutions 2020-339RESOLUTION 2020-339
WHEREAS, an inspection and overhaul of the turbine valves at Platte Generating
Station is performed every three years; and the overhaul was completed during the fall outage in
October of this year; and
WHEREAS, during this inspection, the turbine valves were completely disassembled,
and all components were cleaned, inspected, repaired or replaced; and
WHEREAS, the contract for the Turbine Valve Overhaul — Fa112020 was awarded to
General Electric Steam Power, Inc., from Midlothian, Virginia, in the amount of $221,000.00 at the
July 28, 2020 Council meeting; and
WHEREAS, during the inspection, additional work was required above the base
hours to make repairs to replace the main stop valve pressure seal head bushing and five control
valve lower bushings; and
WHEREAS, the additional work was completed in accordance with the contracted
time and materials for an addition to the scope of work in the amount of $135,862.22, for a final
contract cost of $356,862.22.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 with General Electric Steam
Power, Inc., of Midlothian, Virginia, in the amount of $135,862.22 is hereby approved, and the
Mayor is authorized to sign the Change Order on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, December 22, 2020.