12/08/2020 Resolutions 2020-321RESOLUTION 2020-321 WHEREAS, Water Main Projects 2020-W-2 and 2020-W-3 installed approximately 3,045 linear feet of 8" diameter ductile iron water main. The Greenwich Street work improved domestic supply and increased fire protection to the area, the State Street work resolved the growing number of water main breaks in that area; and WHEREAS, the original contract was awarded by Council on February 25, 2020, in the amount of $734,�75.12 to Myers Construction of Broken Bow, Nebraska; and WHEREAS, during the process of constructing the water mains, materials were added or deducted to complete the work and unit prices were provided in the Contract and specified that the contractor be paid on the basis of actual quantity installed, times the Contract's unit price; and WHEREAS, a significant portion of the reduced quantities is due to less pavement removed and replaced which contributed to the reduced project cost in the amount of $19,524.31; and WHEREAS, the water main had to be lowered beneath the sewer which required additional dewatering, resulting in an additional cost of $12,410.61; and WHEREAS, the original contract amount was $734,775.12, and the total changes to the contract amount to a deduct of $7,113.70, resulting in a final contract cost of $727,661.42. NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 for the construction of Water Main Projects 2020-W-2 and 2020-W-3 in the amount of a deduct of $7,113.70 is approved, and the Mayor is hereby authorized to sign the Change Order on behalf of the City of Grand Island. Adopted by the City Council of the City of Grand Island, Nebraska, December 8, 2020. \ .e.� ;,� ,� Roger G. Steele, Mayor Attest: Qa�� ��� RaNae Edwards, City Clerk Approved as to Form x December 7, 2020 tt City Attorney