11/24/2020 Resolutions 2020-301RESOLUTION 2020-301
WHEREAS, Water Main Project 2020-W-5 installed approximately 1201inear feet of
6" diameter ductile iron water main for water main lowerings in both the Pleasant View
Drive/Phoenix Avenue and Pleasant View Drive/Delaware Avenue intersections to resolve
previously unknown storm sewer and water main conflicts with the two intersections; and
WHEREAS, the original contract was awarded by Council on March 24, 2020, in the
amount of $98,855.06 to Starostka Group, Unlimited, Inc., of Grand Island, Nebraska; and
WHEREAS, during the process of constructing the water main, materials were added
or deducted to complete the work and unit prices were provided in the Contract and specified that the
contractor be paid on the basis of actual quantity installed, times the Contract's unit price; and
WHEREAS, dewatering was not required which contributed to the reduced project
cost in the amount of $8,510.60; and
WHEREAS, the original contract amount was $98,855.06, and the total changes to
the contract amount to a deduct of $8,510.60, resulting in a final contract cost of $90,344.46.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 for the construction of Water
Main Project 2020-W-5 in the amount of a deduct of $8,510.60 is approved, and the Mayor is hereby
authorized to sign the Change Order on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, November 24, 2020.
�
oger G. Steele, Mayor
Attest:
� ����
RaNae Edwards, City Clerk
Approved as to Form tt
November 23, 2020 tt City Attorney