09/22/2020 Resolutions 2020-237R E S O L U T I O N 2020-237
WHEREAS, on May 26, 2020, via Resolution 2020-123, the City of Grand Island
awarded Mid Nebraska Land Developers, LLC of Aurora, Nebraska the bid in the amount of
$239,593.20 for Moores Creek Drain Extension- North Road to Engleman Road; Project No. 2020-
D-1; and
WHEREAS, the completion of such project has been delayed due to the prioritization
of the Old Potash Highway Roadway Improvements; Project No. 2019-P-1; and
WHEREAS, Mid Nebraska Land Developers, LLC has requested an extension from
September 4, 2020 to November 15, 2020 in order to complete the project; and
extension; and
WHEREAS, there will not be any contract amount modification with such time
WHEREAS, the Public Works Department supports such contract extension.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 1 between the City of Grand Island and Mid Nebraska Land
Developers, LLC of Aurora, Nebraska to provide the requested time extension for Moores Creek
Drain Extension- North Road to Engleman Road; Project No. 2020-D-1.
Adopted by the City Council of the City of Grand Island, Nebraska, September 22, 2020.
�