06/23/2020 Resolutions 2020-141RESOLUTION 2020-141
WHEREAS, at the November 12, 2019 meeting, Council awarded the contract for
Water Main Project 2020-W-1— Lincoln and Delta - to the Diamond Engineering Company of Grand
Island, Nebraska in the amount of $119,457.59; and
WHEREAS, during the process of constructing the project, it was found that an 8"
coupling was necessary to connect two sections of the new water main, and an 8" plug was needed
due to a valve size differing from that of record for a total cost for the additional items of $1,175.00;
and
WHEREAS, material were added or deducted to complete the work, and unit prices
were provided in the contract and specified that the contractor be paid on the basis of actual quantity
installed, times the contract's unit price, and this amounted to a deduct of $609.16; and
WHEREAS, the total amount of changes to the contract is $565.84, for a total
contract amount of $120,023.43.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 in the amount of $565.84 to
the contract for Water Main Project 2020-W-1 — Lincoln and Delta — is approved and the Mayor is
hereby authorized to sign the Change Order on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, June 23, 2020.
e. �..... �G/ • ..=.�`��-.
Rog . Steele, Mayor
f
Attest:
��� �
RaNae Edwards, City Clerk
Approved as to Form tt
June 22, 2020 tt i Attorney