05/12/2020 Resolutions 2020-113RESOLUTION 2020-113
WHEREAS, at the February 25, 2020 meeting, Council approved a maintenance
project for the substation transformers that provide power to the City to Transfluid Services, Inc., of
Houston, Texas; and
WHEREAS, during the project, the contractor, Transfluid Services, Inc., discovered
rust inside of one regulator cabinet that needed to be cleaned and sealed; and one of the transformers
at Platte Generating Station had a faulty pressure sensor that was allowing moisture into the
transformer; and
WHEREAS, neither of these items were included in the scope of the bid package, but
both items needed to be addressed while the transformers were already out of service; and
WHEREAS, the original amount of the contract was $261,762.50, and this Change
Order is for $7,879.70 which increases the total contract by approximately 3% to $269,642.20.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 to the Transformer
Maintenance Project is approved, and the Mayor is hereby authorized to sign the Change Order on
behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, May 12, 2020.
Attest:
Ka� o.u�.