11/12/2019 Resolutions 2019-339I
�i
RESOLUTION 2019-339
WHEREAS, on August 28, 2018, via Resolution 2018-252, the City of Grand Island
awarded The Diamond Engineering Company of Grand Island, Nebraska the bid in the amount of
$1,794,404.38 for Sycamore Street Underpass Rehabilitation; Project No. 2017-U-1; and
WHEREAS, on August 27, 2019, via Resolution No. 2019-258, City Council
approved Change Order No. 2, at no cost for the extension of the substantial completion date from
August 1, 2019 to November 12, 2019, with final completion extension from September 30, 2019 to
January 7, 2020 in order to complete the project; and
WHEREAS, the completion of such project has been delayed due to weather
conflicts, along with the need for additional work; and
WHEREAS, The Diamond Engineering Company has requested an extension of the
substantial completion date from November 12, 2019 to May 1, 2019, with final completion
extension from January 7, 2020 to May 15, 2020 in order to complete the project; and
WHEREAS, there is also additional work necessary to refeed the underpass lighting
and install a new electrical service, along with additional concrete repair and lowering of a gas main
due to a storm sewer conflict; and
WHEREAS, the cost of Change Order No. 2 is $74,820.00, resulting in a revised
contract amount of $1,869,224.38.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 2 between the City of Grand Island and The Diamond
Engineering Company of Grand Island, Nebraska for Sycamore Street Underpass Rehabilitation;
Project No. 2019-U-1.
Adopted by the City Council of the City of Grand Island, Nebraska, N
Attest:
� aJ2._ �.�Ll,t�0�1�Qc�
RaNae Edwards, City Clerk
�
�
Ro� G. Steele, Mayor
12, 2019.
Approved as to Form II
November 12, 2019 � Attomey