08/27/2019 Resolutions 2019-252RESOLUTION 2019-252
WHEREAS, at the Marc�i 26, 2019 meeting, Council awarded the contract far Water
Main Project 2018-W-8 at the intersection of Riverside Drive and Holcomb Street to the Diamond
Engineering Company of Grand Island, Nebraska, in the amount of $79,171.20; and
WHEREAS, additional items were required to complete the project due to
encountering groundwater, and dewatering was required for seven days; and
WHEREAS, a storm sewer manhole construction differed from that of record, and a
portion of storm sewer need to be replaced with 12" C900 pipe instead of the planned 15" RCP,
making the total cost for the addition items $11,696.00; and
WHEREAS, additional pavement removal and replacement was required for the
dewatering well installation, additional sidewalk removal, and replacement for proper ADA
configuration amount to $511.19; and
WHEREAS, the original contract was for $79,171.20 and the changes to the contract
amounted to an additional $12,207.19, for a total contract amount of $91,378.39.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 to the contract for Water
Main Project 2018-W-8 is approved, and the Mayor is hereby authorized to sign the Change Order
on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, August 27, 2019.