08/13/2019 Resolutions 2019-240RESOLUTION 2019-240
WHEREAS, at the October 23, 2018 meeting, Council awarded the contract for
Burdick Generating Station Gas Turbine Control System to ABB Inc., of Cleveland, Ohio, in the
amount of $799,371.42; and
WHEREAS, during the installation of the HMI software that communicates with the
distributive control system, the existing computers were found to be not compatible with the newer
software and were required to be upgraded; and
WHEREAS, two new analog input cards that were used from existing equipment
failed, and the purchase of two digital input cards were needed for additional points; and
WHEREAS, this wark was beyond the original base scope of work for an additional
cost of $38,089.74, for a total contract amount of $837,461.16.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 in the amount of $3 8,089.74,
for the Burdick Station Gas Turbine Control System, is approved and the Mayor is hereby authorized
to sign the Change Order on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, August 13, 2019.
Attest:
�� ��.��..
RaNae Edwards, City Clerk
G. Steele, Mayor
Approved as to Form tt
August 12, 2019 tt Ci Attorney