06/11/2019 Resolutions 2019-190RESOLUTION 2019-190
WHEREAS, the City Engineer/Public Works Director issued a Certificate of Final
Completion for Sanitary Sewer Manhole Flow Monitoring / Rehabilitation; Project No. 2018-
WWTP-2 certifying that The Diamond Engineering Company of Grand Island, Nebraska, under
contract, has completed such project for the total construction amount of $238,486.71; and
WHEREAS, the City Engineer/Public Works Director recommends the acceptance of
the project; and
WHEREAS, additional project costs equate to $17,412.49, as shown
Additional Costs:
The Grand Island Inde endent Advertisin $ 121.83
Ci of Grand Island Public Works En ineerin Services $ 891.10
McMaster-Carr Su lies $ 1,248.14
Kell Su I Su lies $ 2 348.42
JMBorer Com anies Post Powder Coatin $ 720.00
Justin Meader Flow Meters & ISCO Cellular Modems $ 12,083.00
Additional Costs = $ 17,412.49
WHEREAS, the Mayor concurs with the recommendation of the City Engineer/Public Works
Director; and
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Certificate of Final Completion for the
Sanitary Sewer Manhole Flow Monitoring / Rehabilitation; Project No. 2018-WWTP-2 is hereby
confirmed for the total amount of $255,899.20.
Adopted by the City Council of the City of Grand Island, Nebraska, June 11, 2019.
Attest:
���,�..--�` �. `�
- _..--°'` .����, �
Aaro chmid, City Clerk Pro Tem
��1
Roge • . Steele, Mayor
Approved as to Form tt
June11, 2019 tt ity 6rney