05/14/2019 Resolutions 2019-158j
,��
RESOLUTION 2019-158
WHEREAS, at the January 22, 2019 Council meeting, Council awarded the contract
for Precipitator, Bottom Ash and Boiler Industrial Cleaning at Platte Generating Station — Spring
2019 Outage to Meylan Enterprises, Inc., of Omaha, Nebraska in the amount of $156,178.27; and
WHEREAS, during the outage additional work beyond the base bid scope was
required to remove split coal from railroad tracks, greater than normal volumes of fly ash from the
precipitator and excessive build-up of lime in the Spray Dry Absorber, resulting in an increase in the
cost of the overall contract; and
WHEREAS, Meylan Enterprises had all of the manpower and equipment on-site to
perform the additional work and this additional cost was based on unit pricing for services included
the original bid documents in the event of the addition or deletion of work scopey by the contractor;
and
WHEREAS, the work included vacuum services, hydro-blasting services and the use
of specialty three-dimensional cleaning nozzles used specifically for cleaning the SDA vessel and;
WHEREAS, the additional work performed by Meylan Enterprises, Inc., amounted to
$20,291.50 including applicable taxes for the work for a total contract amount of $176,469.77.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 in the amount of $20,291.50
is approved and the Mayor is hereby authorized to sign the Change Order on behalf of the City of
Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, May 14, 2019.