01/08/2019 Resolutions 2019-16RESOLUTION 2019-16
WHEREAS, Water Main Project 2018-W-3 installed approximately 1,7401inear feet
of new City water main within Golden Age Subdivision to provide increased capacity and fire
protection for the area; and
WHEREAS, the original contract was awarded by City Council on February 13, 2018,
in the amount of $199,795.07 to Van Kirk Brothers Contracting of Sutton, Nebraska; and
WHEREAS, additional items were required to complete the project due to rubble
encountered when excavating, utility sizes differing from sizes of record, and poor condition of
existing infrastructure and the cost of this work is $2,661.00; and
WHEREAS, during the process of constructing the water main, materials were added
or deducted to complete the project and a significant portion of the quantity overage was due to
additional pavement and sidewalk repair for replacing deteriorating existing hard surfacing. This
total is $7,555.43 for a total cost change of $10,216.43.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 in the amount of $10,216.43,
for the construction of Water Main Project 2018-W-3 is approved and the Mayor is hereby
authorized to sign the Change Order on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, January 8, 2019.
Attest:
��n�����
RaNae Edwards, Ciry Clerk
�.
Roger G. Steele, Mayor
Approved as to Form �
January 7, 2019 R ity torney