12/18/2018 Resolutions 2018-382RESOLUTION 2018-382
WHEREAS, on June 12, 2018, via Resolution No.2018-168, the City of Grand Island
awarded Cheever Construction of Lincoln, Nebraska the bid in the amount of $1,122,400.00 for
renovations to the Edith Abbott Memorial Library; and
WHEREAS, on October 23, 2018, via Resolution No. 2018-304, City Council approved
Change Order No. 1, in the amount of $3,365.93 to such project, modifying the total contract to
$1,125,765.93; and
WHEREAS, it has been determined that modifications need to be made to allow for power
modifications to a meeting room for AV equipment, relocation of a meeting room light, additional
wall repairs, painting and wall coverings and a water cooler GFCI breaker; and
WHEREAS, such modifications have been incorporated into Change Order No. 2 in the
amount of $1,546.00 and Change Order 3 in the amount of $9,040.36; and
WHEREAS, the result of both change orders will increase the contract amount by
$10,586.36, for a revised contract price of $1,136,352.29; and
WHEREAS, The Grand Island Public Library Foundation is responsible for financing all
costs for this project that are not provided by the Grimminger estate funds from the 295 Special
Project Account and project-specific grant funds received by the City, as per Resolution No. 2018-
164 approved by the City Council on June 12, 2018.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE
CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 2 in the amount of $1,546.00 and Change Order 3 in the
amount of $9,040.36, for a total increase of $10,586.36 between the City of Grand Island and
Cheever Construction of Lincoln, Nebraska to provide the modifications for a revised contract price
of $1,136,352.29.
Adopted by the City Council of the City of Grand Island, Nebraska, December 18, 2018.
Attest:
�- � �
Aaron id, City Clerk Pro Tem
�: `
Roge . Steele, Mayor
Approved as to Form tt
December 17, 2018 tt ity A ney