11/20/2018 Resolutions 2018-348RESOLUTION 2018-348
WHEREAS, on May 22, 2018, via Resolution No.2018-145, the City of Grand Island
awarded The Diamond Engineering Company of Grand Island, Nebraska the bid in the amount of
$205,966.99 for Sanitary Sewer Manhole F1ow Monitoring / Rehabilitation; Project No. 2018-
WWTP-2; and
WHEREAS, on June 26, 2018, via Resolution No. 2018-187, City Council approved
Change Order No. 1, in the amount of $29,488.62, to such project to allow for installation of an
additional flow meter, which will capture South Interceptor Sewer Shed 3; and
WHEREAS, on September 25, 2018, via Resolution No. 2018-282, City Council
approved Change Order No. 2 to such project to allow additional time for completion; and
WHEREAS, such change order did not affect the contract amount of $235,455.61;
and
WHEREAS, it has been determined that two (2) of the three (3) manholes being
rehabilitated are five (5) foot in diameter and not the originally bid four (4) foot diameter; and
WHEREAS, Change Order No. 3 is necessary to account for the discrepancy and
complete the project; and
WHEREAS, the result of such modifications will increase the contract amount by
$3,050.00, resulting in a revised contract amount of $238,505.61.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 3 in the amount of $3,050.00 between the City of Grand Island
and The Diamond Engineering Company of Grand Island, Nebraska to provide the modifications.
Adopted by the City Council of the City of Grand Island, Nebraska, November 20, 2018.