09/11/2018 Resolutions 2018-269R E S O L U T I O N 2018-269
WHEREAS, on March 27, 2018, via Resolution No.2018-85, the City of Grand Island
awarded Midlands Contracting, Inc. of Kearney, Nebraska the bid in the amount of $1,647,665.35
for Lift Station No. 11 Relocation — 2018; Project No. 2018-5-1; and
WHEREAS, on June 12, 2018, via Resolution No. 2018-160, City Council approved
Change Order No. 1, which added pay items for directional drilling at the intersection of Custer
Avenue & 13�` Street and at the detention cell north of this area, as well as adjusted quantities for
such work for a contract reduction of $15,657.70; and
WHEREAS, on July 10, 2018, via Resolution No. 2018-203, City Council approved
Change Order No. 2, which established a new unit price for bedding the force main in native sand,
resulting in a unit price reduction of $1.97 over originally bid granular bedding; and
WHEREAS, it has been determined that modifications need to be made to allow for addition
of an ADA ramp, abandonment of water service at Walnut Middle School, reconstruction of storm
sewer inlet, pavement stripe on Custer Avenue, and traffic control credit on Custer Avenue; and
WHEREAS, such modifications have been incorporated into Change Order No. 3;
and
WHEREAS, the result of such modifications will increase the original contract
amount by $8,780.80, resulting in a revised contract amount of $1, 640,788.45.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 3 in the amount of $8,780.80 between the City of Grand Island
and Midlands Contracting, Inc. of Kearney, Nebraska to provide the modifications.
Adopted by the City Council of the City of Grand Island, Nebraska, September 11, 2018.
Attest:
�o. � -
RaNae Edwards, City Clerk
�/ �4/ � . .��
. �� •� � ��
Approved as to Form tt
September 10, 2018 tt�ty� torney