09/11/2018 Resolutions 2018-267RESOLUTION 2018-267
WHEREAS, at the January 23, 2018 meeting, Council awarded the contract for Water
Main District 471T in the amount of $141,755.80 to Van Kirk Brothers Contracting of Sutton,
Nebraska; and
WHEREAS, during construction, the following required alterations were
encountered:
1) Change #1: Additional items were needed: A 6" x 22.5° bend was required to install a
hydrant to proper grade and a buried concrete slab needed to be removed and replaced for a
total cost of $680.00.
2) Change #2: Materials were added or deducted to complete the work. Unit prices were
provided in the contract and specified that the contractor be paid on the basis of actual
quantity installed, times the contract's unit price. This amount added $954.80 to the amount
due.
WHEREAS, the contract's amount needs to be modified due to the afore mentioned
causes for the project in the amount of $1,634.80, for a final contract amount of $143,390.60.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 with Van Kirk Brothers
Contracting is approved in the amount of $1,634.80, and the Mayor is hereby authorized to sign the
Change Order on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, September 11,2018.
Attest:
�� �.��a�.
RaNae Edwards, City Clerk
�� 4� .�.
�:' :�'� . �
Approved as to Form tt
September 10, 2018 tt ity� orney