RESOLUTION 2018-202
WHEREAS, on March 28, 2017, via Resolution No.2017-88, the City of Grand Island
awarded The Diamond Engineering Company of Grand Island, Nebraska the bid in the amount of
$2,306,455.27 for Lift Station No. 20 Upgrade and Force Main Rehabilitation & Lift Station No. 14
Abandonment; Project No. 2017-S-1; and
WHEREAS, on October 10, 2017, via Resolution No. 2017-276, City Council
approved Change Order No. 1 to the original agreement, which allowed for replacement of Manhole
NO. 75 and extended the completion date from March 15, 2018 to April 14, 2018 in the amount of
$97,640.79; and
WHEREAS, on Apri110, 2018, via Resolution No. 2018-99, City Council approved
Change Order No. 2 at no cost, which allowed for a time extension from April 14, 2018 to June 30,
2018; and
project; and
and
WHEREAS, it has been determined that additional time is necessary to complete such
WHEREAS, such modifications have been incorporated into Change Order No. 3;
WHEREAS, there will be no cost associated with such time extension, leaving the
contract agreement amount of $2,404,096.06; and
WHEREAS, the project completion date will be extended from June 30, 2018 to
August 31, 2018.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 3, at no additional cost, between the City of Grand Island and
The Diamond Engineering Company of Grand Island, Nebraska to provide the modifications.
Adopted by the City Council of the City of Grand Island, Nebraska, July 10, 2018.