06/26/2018 Resolutions 2018-192;
RESOLUTION 2018-192
WHEREAS, on October 11, 2012 Grand Island City Council, by Resolution No.
2011-307, approved the consulting agreement with Black & Veatch of Kansas City, Missouri;
for project management, collection system master planning and conceptual designs for the
Northeast Interceptor sewer, Collection System rehabilitation and Wastewater Treatment
rehabilitation in the amount of $1,121,160.00, and
WHEREAS, on April 24, 2012 Grand Island City Council, by Resolution No.
2012-111, approved Amendment No. 1 allowed for the continuation of the design effort to final
design and bidding, in the amount of $1,910,075.00; and
WHEREAS, on August 28, 2012 Grand Island City Council, by Resolution No.
2012-229, approved Amendment No. 2 to add CDBG guideline provisions, and provided for
construction engineering services for the Lift Station No. 7 Improvements and 4�' Street to 5�'
Street; Eddy Street to Vine Street rehabilitation, in the amount of $53,000; and
WHEREAS, on November 13, 2012 Grand Island City Council, by Resolution
No. 2012-329, approved Amendment No. 3 allowed for construction engineering services and
resident inspection during construction for the Sth Street Sanitary Sewer Improvements, as well
as for the South & West Sewer Interceptor Improvements with the consulting firm Black &
Veatch of Kansas City, Missouri, in the amount of $265,754.00; and
WHEREAS, on February 12, 2013 Grand Island City Council, by Resolution No.
2013-34, approved Amendment No. 4 allowed for the review to the "Report on Revenue
Requirements, Cost of Service and Rates for Wastewater", in the amount of $30,000; and
WHEREAS, on February 12, 2013 Grand Island City Council, by Resolution No.
2013-35, approved Amendment No. 5 allowed preliminary design engineering services in Phase
II of the North Interceptor Sewer planning, and final biding documents for Phase II-B North
Interceptor Sewer with the consulting firm Black & Veatch of Kansas City, Missouri in the
amount of $451,896; and
WHEREAS, on May 14, 2013 Grand Island City Council, by Resolution No.
2013-2013-148, approved Amendment No. 6 allowed fee compensation in engineering services
that were not specifically identified in the original design agreement; Consulting Engineering
Construction Phase Services, and Resident Inspection During Construction for Phase I; North
Interceptor Sewer Construction, in the amount of $719,617.00; and
WHEREAS, on May 14, 2013 Grand Island City Council, by Resolution No.
2013-149, approved Amendment No. 7, which provides for Consulting Engineering Construction
Phase Services, Resident Inspection During Construction and Integration Services for
Headworks Improvements Construction with the consulting firm Black & Veatch of Kansas
City, in the amount of $1,878,450.00; and
Approved as to Form tt
May 14, 2013 tt�ity orney
WHEREAS, on December 17, 2013 Grand Island City Council, by Resolution
No. 2013-400, approved Amendment No. 8, which allowed Final Design Phase Services for
North Interceptor Phase 2A & 2C (Broadwell Avenue to 7�'/Sky Park Road & Lift Station No. 19
to Web Road), as well as Bidding Phase Services for all 3 phases of the North Interceptor
(Broadwell Avenue to 7th/Sky Park Road, Webb Road to Broadwell Avenue, and Lift Station No.
19 to Webb Road). Bidding Phase Services originally included in Amendment No. 5 for the
North Interceptor were deleted and combined in this amendment; and
WHEREAS, on September 9, 2014 City Council approved, by Resolution No.
2014-278 for Amendment No. 9 in the amount of $1,846,639.00 to this agreement. This
amendment allowed for construction phase services and resident observation services during
construction on North Interceptor 2; and
WHEREAS, on April 14, 2015 City Council approved, by Resolution No. 2015-
92 for Amendment No. 10 to allow for an update to the Wastewater Financial Plan. Such
amendment increased the original agreement by $46,000.00, resulting in a revised agreement of
$9,227,115.00; and
WHEREAS, Amendment No. 11 will allow for redistribution of tasks form the
original agreement and focus on a Collection System Master Plan Initial Review, Wastewater
Financial Plan Update, and Collection System Master Plan Complete Update; and
WHEREAS, there is no cost associated with Amendment No. 11, resulting in the
agreement remaining at a cost of $9,227,115.00.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL
OF THE CITY OF GRAND ISLAND, NEBRASKA, that such Amendment No. 11 to the
agreement with Black & Veatch of Kansas City, Missouri is hereby approved.
BE IT FURTHER RESOLVED, that the Mayor is hereby authorized and directed
to execute such Amendment No. 11 on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, June 26, 2018.
Attest:
�a. a.a. Q l�►�A3��
RaNae Edwards, City Clerk
-2-
Je m L. Je sen yor