06/26/2018 Resolutions 2018-188RESOLUTION 2018-188
WHEREAS, on May 23, 2017, via Resolution No.2017-151, the City of Grand Island
awarded The Diamond Engineering Company of Grand Island, Nebraska the bid in the amount of
$304,380.16 for Sanitary Sewer Collection System Rehabilitation — Various Locations; Project No.
2017-S-2A; and
WHEREAS, on August 22, 2017, via Resolution No. 2017-230, Grand Island City
Council approved Change Order No. 1 in the amount of 44,632.63, which allowed for repair of
Manhole No. 477; the base had fallen in and was severely deteriorated; and
WHEREAS, on April 24, 2018, via Resolution No. 2018-111, Grand Island City
Council approved Change Order No. 2 at no additional cost to allow for an extension of the project
completion date from Apri120, 2018 to July 15, 2018; and
WHEREAS, it is necessary to rectify quantities of bid items to be incorporated into
the referenced project, which will result in an overall contract increase of $37,339.32, for a revised
contract amount of $386,352.11 to complete such project; and
WHEREAS, such modifications have been incorporated into Change Order No. 3.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 3, in the amount of $37,339.32, between the City of Grand
Island and The Diamond Engineering Company of Grand Island, Nebraska to provide the
modifications.
Adopted by the City Council of the City of Grand Island, Nebraska, June 26, 2018.
Attest:
�a. o�. _C�c,�o,r�
RaNae Edwards, City Clerk
Jere . Jen n, a or
Approved as to Form tt
June 22, 2018 tt mey