06/26/2018 Resolutions 2018-183RESOLUTION 2018-183
WHEREAS, at the December 12, 2017 Council meeting, Council awarded the
contract for Water Main Project 2018-W-1 — 17th Street from Broadwell Avenue to Elm Street to
Myers Construction, Inc., of Broken Bow, Nebraska, in the amount of $368,123.84; and
WHEREAS, during construction, an unknown fiber-optic vault that serves the north
part of Grand Island was discovered at the southwest corner of 17th and Elm Streets; and
WHEREAS, the obstruction required changing the water main alignment, moving it
out into the parking lane of 17th Street; and
WHEREAS, as a result of the needed relocation, the amount of roadway and curb
removal replacements increased; and
WHEREAS; Change Order # 1 in the amount of $26,474.49 was prepared, resulting in
a final contract amount of $394,598.33.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 in the amount of $26,474.49
is approved, and the Mayor is hereby authorized to sign the Change Order on behalf of the City of
Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, June 26, 2018.