02/27/2018 Resolutions 2018-52RESOLUTION 2018-52
WHEREAS, at the March 14, 2017 Council meeting, Council awarded the contract
for construction of Water Main District 469T to The Diamond Engineering Company of Grand
Island, Nebraska, in the amount of $284,906.56; and
WHEREAS, actual unit quantities needed for construction were higher than the
original estimate of quantities needed for the project; and the amount due was based on unit prices
times the contract's unit price, so the contractor needs to paid on the basis of actual quantity
installed; and
WHEREAS, as a result of these, Change Order #1 was prepared for an additional
$2,150.23, for a total contract amount of $287,056.79.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order # 1 for the construction of Water
Main District 469T is hereby approved, and the Mayor is hereby authorized to sign Change Order #1
on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, February 27, 2018.
Attest:
�� � ���
RaNae Edwards, City Clerk
erem L. J en, Mayor
Approved as to Form tt
February 27, 2018 � ity orney