10/24/2017 Resolutions 2017-297RESOLUTION 2017-297
WHEREAS, at the March 14, 2017 meeting, Council awarded the contract for
construction of the Composite Elevated Water Storage Tank, to Landmark Structures of Fort Worth,
Texas, in the amount of $3,454,200.00; and
WHEREAS, during the design phase, an investigation of the surrounding area found
that there would not be enough drainage to facilitate draining the tank for inspection without
flooding a future housing development; and
WHEREAS, to address this issue, a pump was designed to pump the remaining water
from the elevated storage into the water system; and
WHEREAS, as a result of these design changes, Change Order # 1 was prepared for
$102,255.00 for a total contract amount of $3,556,455.00.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 for the construction of the
Composite Elevated Water Storage Tank, is hereby approved and the Mayor is hereby authorized to
sign Change Order #1 on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, October 24, 2017.
Attest:
��� ���-�-�.
RaNae Edwards, City Clerk