09/12/2017 Resolutions 2017-243RESOLUTION 2017-243
WHEREAS, the City Engineering/Public Works Director for the City of Grand Island
issued a Certiiicate of Final Completion for Project No. 2017-CR-1, installation of Curb Ramps,
certifying that Galvan Construction, Inc. of Grand Island, Nebraska, under contract, has completed
the curb ramp installation; and
WHEREAS, the City Engineer/Public Works Director recommends the acceptance of
the project; and
WHEREAS, the Mayor concurs with the recommendation of the City Engineer/Public
Works Director.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that the Certificate of Final Completion for Project
No. 2017-CR-1, installation of curb ramps, is hereby confirmed, for a total project cost of
$103,033.36.
Adopted by the City Council of the City of Grand Island, Nebraska, September 12, 2017.