09/12/2017 Resolutions 2017-241� ,
RESOLUTION 2017-241
WHEREAS, at the April 11, 2017 Council meeting, Council awarded the contract for
Vehicle Storage Building and Warehouse at 1306 West 3rd Street, to Chief Construction Company of
Grand Island, Nebraska, in the amount of $372,613.00; and
WHEREAS, the existing concrete pavement just west of the new garage was deemed
to slope towards the proposed building slab and to alleviate water from flowing toward the proposed
building, 936 square feet of existing pavement was removed, regraded and replaced at a cost of
$6,808.93; and
WHEREAS, an old foundation was discovered during excavation and inspection of
the soil in this location deemed the soil to be unsuitable as a base material and the soil had to be
removed and replaced at a cost of $8,767.11; and
WHEREAS, the connection point for the sewer be changed from a manhole toe the
existing service line and in order to facilitate the extra pavement removal and pipe installation, an
extra cost of $6,257.47 was incurred; and
WHEREAS, as a result of these design changes, Change Order # 1 was prepared for an
additional $21,833.51, for a total contract amount of $394,446.51.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 for the Vehicle Garage &
Warehouse Project at 1306 W. 3rd Street, is hereby approved and the Mayor is hereby authorized to
sign Change Order #1 on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, September 12, 2017.
Attest:
RaNae Edwards, City Clerk
J emy L. J sen, ayor
Approved as to Form tt
September 11, 2017 � tyA rney