08/11/2015 Resolutions 2015-214 RESOLUTION 2015-214
WHEREAS, On September 9, 2014, by Resolution No. 2014-284, City Council
awarded,Project 2013-S-4,North Interceptor Phase II to S.J. Louis Construction,Inc.of Rockville,
Minnesota, in the amount of$21,479,537.50; and
WHEREAS, on February 10, 2015, by Resolution No. 2015-39, City Council
approved Change Order No. 1, which established new unit prices for installed storm and sanitary
sewers which are embedded with native sand material in lieu of the imported granular embedment
specified in the contract documents; and
WHEREAS,on March 24,2015,by Resolution No.2015-74,City Council approved
Change Order No. 2, which changed the methodology of the trenchless crossing from micro
tunneling to a direct jacked tunnel using a tunnel boring machine at both Broadwell Avenue/Capital
Avenue and Webb Road/Northwest Crossings property at Capital Avenue and resulted in a deduction
of$210,003.48, for a revised contract amount of$21,269,534.02; and
WHEREAS on June 23,2015,by Resolution No.2015-160,City Council approved
Change Order No. 3,which addressed unknown and unplanned restraint at the existing 18"waterline
that crosses Capital Avenue just east of Webb Road;additional storm sewer work near St.Paul Road
as needed to fill in a portion of the utility ditch and provide access to the new manhole; and
— finalization of the As-Built quantities for Phase II(Part B)and resulted in an increase of$56,540.88,
for a revised contract amount of$21,326,074.90; and
WHEREAS,Change Order No.4 allows for an open cut at the intersection of Capital
Avenue and Broadwell Avenue for installation of the north interceptor,rerouting of the dewatering
discharge, and several modifications to the existing storm sewer at this intersection; and
WHEREAS, an overall net change of the contract amount will be a decrease of
$40,651.39, which results in an adjusted contract amount of$21,285,423.51.
NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND,NEBRASKA,that authorization to proceed with Change Order
No. 4 with S.J. Louis Construction, Inc. of Rockville, Minnesota is hereby approved; and
BE IT FURTHER RESOLVED,that the Mayor is hereby authorized and directed to
execute such Change Order No.4,North Interceptor Phase II,Project 2013-S-4 on behalf of the City
of Grand Island. •
Approved as to Form • -- ..111
September 10,2013 a City + ney
Adopted by the City Council of the City of Grand Island, Nebraska, August 11, 2015.
.1, ....A1L.A. ._.�
Jerem . Jen.en,la .A.
Attest:
on• • a) f 0
RaNae Edwards, City Clerk
-2 -