08/11/2015 Resolutions 2015-213 RESOLUTION 2015-213
WHEREAS,on January 13,2015,by Resolution 2015-9,the City Council of the City
of Grand Island approved the bid of The Diamond Engineering Co. of Grand Island,Nebraska for
construction of South Blaine Street Bridge Replacements; Project No. 2014-B-1; and
WHEREAS,the completion of such project has been delayed due to several factors;
and
WHEREAS, The Diamond Engineering Company has requested an extension from
August 1, 2015 to November 30, 2015 in order to complete the project; and
WHEREAS, additional work is necessary to address the existing condition of the
asphalt roadway with an upgrade to concrete pavement; and
WHEREAS,such additional work will add$40,994.72 to the original contract,for a
revised total of$425,978.67; and
WEREAS, the Public Works Department supports such contract extension and
additional roadway work.
NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND,NEBRASKA,that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 1 between the City of Grand Island and The Diamond
Engineering Co. of Grand Island, Nebraska to provide the modifications of South Blaine Street
Bridge Replacements; Project No. 2014-B-1.
Adopted by the City Council of the City of Grand Island, Nebraska, August 11, 2015.
Jere 1101 . Jen,en, 0 yor'
Attest:
RaNae Edwards, City Clerk