06/23/2015 Resolutions 2015-160 -- RESOLUTION 2015-160
WHEREAS, On September 9, 2014, by Resolution No. 2014-284, City Council
awarded,Project 2013-S-4,North Interceptor Phase II to S.J. Louis Construction,Inc.of Rockville,
Minnesota, in the amount of$21,479,537.50; and
WHEREAS, on February 10, 2015, by Resolution No. 2015-39, City Council
approved Change Order No. 1, which established new unit prices for installed storm and sanitary
sewers which are embedded with native sand material in lieu of the imported granular embedment
specified in the contract documents; and
WHEREAS,on March 24,2015,by Resolution No.2015-74,City Council approved
Change Order No. 2, which changed the methodology of the trenchless crossing from micro
tunneling to a direct jacked tunnel using a tunnel boring machine at both Broadwell Avenue/Capital
Avenue and Webb Road/Northwest Crossings property at Capital Avenue and resulted in a deduction
of$210,003.48, for a revised contract amount of$21,269,534.02; and
WHEREAS,Change Order No. 3 allows for payment in order to restrain the existing
18"waterline as part of Phase II(Section B), additional storm sewer and utility ditch work near St.
Paul Road, and finalization of As-Built quantities in Phase II(Section B).
WHEREAS, an overall net change of the contract amount will be an increase of
$56,540.88, which results in an adjusted contract amount of$21,326,074.90.
NOW, THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND,NEBRASKA, that authorization to proceed with Change Order
No. 3 with S.J. Louis Construction, Inc. of Rockville, Minnesota is hereby approved; and
BE IT FURTHER RESOLVED,that the Mayor is hereby authorized and directed to
execute such Change Order No. 3,North Interceptor Phase II,Project 2013-S-4 on behalf of the City
of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska,June 23, 2015.