06/09/2015 Resolutions 2015-145 RESOLUTION 2015-145
WHEREAS,on June 10,2014,by Resolution 2014-163,the City Council of the City
of Grand Island approved the bid of Van Kirk Brothers Contracting of Sutton, Nebraska for
construction of Sanitary Sewer District No. 528 and No. 530T; and
WHEREAS,on February 10, 2015 City Council approved Resolution No. 2015-38,
which allowed for an extension from June 15,2015 to July 27,2015 for Sanitary Sewer District No.
528 and from March 15, 2015 to April 24, 2015 for Sanitary Sewer District No. 530T in order to
complete the projects; and
WHEREAS, on March 24, 2015 City Council approved Resolution No. 2015-75,
which changed direct borings at two(2)locations;Guenther Road and 1,000 feet south of Guenther
Road, at US Highway 281, to open cuts at each location. Such change resulted in a net credit of
$47,507.46, for a revised total contract amount of$3,326,611.24 (528= $1,602,306.30 & 530T =
$1,724,304.94).
WHEREAS, the completion of Sanitary Sewer District No. 530T has been delayed
due to several factors; and
WHEREAS, such delays have resulted in additional work days; and
WHEREAS,Van Kirk Brothers Contracting has requested an extension from April
24,2015 to June 10,2015 for Sanitary Sewer District No. 530T in order to complete the project;and
WEREAS, the Public Works Department supports such contract extension.
NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND,NEBRASKA,that the Mayor be, and hereby is, authorized and
directed to execute Change Order No. 1 between the City of Grand Island and Van Kirk Brothers
Contracting of Sutton,Nebraska to provide the modifications of Sanitary Sewer District No. 530T.
Adopted by the City Council of the City of Grand Island,Nebraska, June 9, 2015.
A vat .; �:•
Jere , L. J%nse ayor
Attest:
. I
RaNae Edwards, City Clerk
•
Approved as to Form A !.►t!n'
Iv
June 8,2015 0 City A • ney