10/28/2014 Resolutions 2014-323 RESOLUTION 2014-323
WHEREAS,IES Commercial,Inc.,of Holdrege,Nebraska was awarded the contract
for construction of Substation J, at the September 24, 2013 City Council meeting; and
WHEREAS, during construction, several minor changes were made to improve the
design and correct minor deficiencies; and because of these changes, the completion deadline has
been extended from September 1, 2014 to November 28, 2014; and
WHEREAS, due to the separation of the control building and relay panels from the
construction contract, some labor and material quantities were unknown when contracts were
originally awarded; and
WHEREAS,Change Order#2 was prepared for a contract adjustment of an increase
in the amount of$74,889.00, resulting in a final contract amount to date of$2,654,567.38, and a
completion deadline of November 28, 2014.
NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND,NEBRASKA,that Change Order#2 with IES Commercial,Inc.,
of Holdrege,Nebraska,resulting in an increased cost of$74,889.00,for a final contract price to date
of$2,645,567.38, is hereby approved.
Adopted by the City Council of the City of Grand Island, Nebraska, October 28, 2014.
Alif '. ..
Vav 'cek, Mayor
Attest:
RaNae Edwards, City Clerk
Approved as to Form °
October 27,2014 0 City Attorney