05/27/2014 Resolutions 2014-119 — RESOLUTION 2014-119 WHEREAS, AMEC of Tucker, Georgia, was awarded the contract for Air Quality Control System(AQCS)at Platte Generating Station, at the January 8,2013 City Council meeting; and WHEREAS,during the initial engineering process,the requirements for the roofs to meet FM Global standards were not included in the specification; and WHEAREAS,FM Global provides insurance for power plants,and a higher standard for wind uplift is a requirement on the roof panels. These standards require more structural steel to fasten the roof panels to the structure; and WHEAREAS,the original Engineer,Kiewit Engineering,and Grand Island Utilities Staff agree that the change is justified and reasonable; and WHEREAS,Change Order#2 was prepared for a contract adjustment of an additional amount of$54,401.00, resulting in a final contract amount of$42,140,242.00. NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF -- THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #2 with AMEC of Tucker, Georgia,resulting in an additional cost of$54,401.00,for a final contract price of$42,140,242.00,is hereby approved. Adopted by the City Council of the City of Grand Island,Nebraska, May 27, 2014. (20111111111p' APT Vav'l eek, Mayor Attest: 0SM as_ F,S)(,,,)• 0- RaNae Edwards, City Clerk Approved as to Form a 41t,g1,4; May 27,2014 a City' :mey