05/27/2014 Resolutions 2014-119 — RESOLUTION 2014-119
WHEREAS, AMEC of Tucker, Georgia, was awarded the contract for Air Quality
Control System(AQCS)at Platte Generating Station, at the January 8,2013 City Council meeting;
and
WHEREAS,during the initial engineering process,the requirements for the roofs to
meet FM Global standards were not included in the specification; and
WHEAREAS,FM Global provides insurance for power plants,and a higher standard
for wind uplift is a requirement on the roof panels. These standards require more structural steel to
fasten the roof panels to the structure; and
WHEAREAS,the original Engineer,Kiewit Engineering,and Grand Island Utilities
Staff agree that the change is justified and reasonable; and
WHEREAS,Change Order#2 was prepared for a contract adjustment of an additional
amount of$54,401.00, resulting in a final contract amount of$42,140,242.00.
NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
-- THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #2 with AMEC of Tucker,
Georgia,resulting in an additional cost of$54,401.00,for a final contract price of$42,140,242.00,is
hereby approved.
Adopted by the City Council of the City of Grand Island,Nebraska, May 27, 2014.